PlumbingIntermediateStormwater

Stormwater Detention Storage-Balance Calculator

Calculate net storage change from average inflow, average outflow, and event duration.

Why it matters: A transparent formula keeps the user-entered hydraulic, gas, or storage basis available for technical review.

User inputs

Enter field measurements

4 inputs
Select I-P or SI units for the entire input set.
gpm or L/sAverage inflow over the stated duration.
gpm or L/sAverage controlled outflow.
hDuration represented by the averages.

Calculated result

Engineering evaluation

Calculation complete—verify project criteria
Net event storage change (ΔV)18,000 gal
Net storage rate (Q_n)
300 gpm

Engineering interpretation

The average-flow balance changes storage by 18000 gal over the event.

Important limitations

  • Screening calculation only. Adopted codes, local criteria, manufacturer data, uncertainty, and professional engineering judgment remain controlling.
  • Average-flow balance only; hydrograph routing, stage-storage-discharge, initial storage, freeboard, tailwater, infiltration, and emergency overflow are omitted.

Engineering knowledge center

Understand the calculation—not just the answer

2026-08-07 · Free Library
Governing relationships
ΔV=(Q_i−Q_o)t
displayed symbols: Q_n
Current substitution

ΔV=(500−200)×1×60=18000.

Calculation sequence

Step-by-step method

  1. Confirm the calculation boundary, units, and source of every input.
  2. Apply the displayed equation to the entered values.
  3. Review the result against governing criteria and documented uncertainty.

Equation legend

Inputs and calculated quantities

Q_i
Average event inflow — gpm or L/s
Q_o
Average event outflow — gpm or L/s
t
Event duration — h
ΔV
Net event storage change — gal
Q_n
Net storage rate — gpm

Engineering calculation disclaimer

These engineering tools are provided for educational, preliminary evaluation, field verification, and commissioning support. Results depend on the accuracy of user-entered information and the assumptions stated for each calculation. Every colored status and comparison is a screening indicator only; project criteria, contract requirements, applicable codes, manufacturer instructions, measurement uncertainty, and authorized engineering judgment govern. The tools do not replace project-specific engineering analysis or the judgment of a licensed professional engineer.

Read the full use and limitation statement