PlumbingAdvancedSanitary Drainage Pumps

Sewage-Ejector Pump Duty Calculator

Assemble a preliminary sewage-ejector flow and head duty point from visible user-approved inputs.

Why it matters: Peaking, static lift, system loss, and discharge condition must be explicit before equipment review.

User inputs

Enter field measurements

6 inputs
Select I-P or SI display units. Convert the entire input set before calculating.
gpm or L/sApproved average or base design inflow.
ratioVisible approved peaking factor.
ft or mStatic elevation head.
ft or mUser-entered loss at required pump flow.
ft or mReceiving-system or discharge residual head.

Calculated result

Engineering evaluation

Calculation complete—verify project criteria
Required sewage-ejector flow (Qᵖ)125 gpm
Preliminary total dynamic head (TDH)
40 ft

Engineering interpretation

The entered basis yields preliminary duty 125 gpm at 40 ft TDH.

Important limitations

  • Sewage/ejector screening only. Do not select equipment from this result alone. Confirm biological, exposure, confined-space and electrical hazards; solids handling; pump/system curves; basin/cycling; duplex redundancy; valves; emergency storage; alarms; receiving pressure; and code criteria.

Motor-driven equipment

Estimate electrical demand and energy use

Use nameplate information and an operating schedule to screen motor input power, current, annual energy, and operating cost. Results update automatically.

Optional companion calculation
Choose the motor nameplate output-power convention.
Rated shaft output, not electrical input.
Used to estimate current; it does not change the hp-based energy result.
Use efficiency at the evaluated load point when available.
Use measured or defensible operating load rather than motor nameplate size alone.
Used only for the estimated current calculation.
Assumes all selected motors operate concurrently at the entered load.
Replace the profile with the actual occupied, process, or control schedule.
$/kWh
Use the applicable marginal utility energy charge; demand charges are not included.

Estimated result

Total motor input power (Pin,total)6.21 kW
Current per motor (I)
9.18 A
Total coincident current (Itotal)
9.18 A
Daily energy (Ed)
50 kWh/day
Annual operating hours (Hy)
2,080 h/year
Annual energy (Ey)
12,925 kWh/year
Annual energy cost (Cy)
$1,551/year

Equations and assumptions

Nameplate-based screening method

Pin=PratedLηmI=1000Pin3VPFEy=NPinhddyCy=Eyce

Horsepower is converted using 1 hp = 0.7457 kW. This estimate assumes steady average load and the entered operating-point efficiency. Voltage and power factor affect estimated current, but hp, load, efficiency, quantity, and schedule establish the energy estimate. VFD speed profiles, cycling, standby power, demand charges, and process variation require separate evaluation.

Technical basis: U.S. Department of Energy — Determining Electric Motor Load and Efficiency

Engineering knowledge center

Understand the calculation—not just the answer

2026-08-07 · Free Library
Governing relationships
Qᵖ=Fᵖ·Qᵢ
TDH=Hˢ+Hᶠ+Hʳ
Current substitution

Qᵖ=1.25×100=125; TDH=20+15+5=40.

Calculation sequence

Step-by-step method

  1. Apply the visible approved peaking factor to base inflow.
  2. Add static, friction, and residual head components.
  3. Review the point against the full system curve and manufacturer data.

Equation legend

Inputs and calculated quantities

Qᵢ
Base design inflow — gpm or L/s
Fᵖ
Approved peaking factor — ratio
Hˢ
Static lift — ft or m
Hᶠ
Piping and fitting loss — ft or m
Hʳ
Required discharge residual head — ft or m
Qᵖ
Required sewage-ejector flow — gpm
TDH
Preliminary total dynamic head — ft

Engineering calculation disclaimer

These engineering tools are provided for educational, preliminary evaluation, field verification, and commissioning support. Results depend on the accuracy of user-entered information and the assumptions stated for each calculation. Every colored status and comparison is a screening indicator only; project criteria, contract requirements, applicable codes, manufacturer instructions, measurement uncertainty, and authorized engineering judgment govern. The tools do not replace project-specific engineering analysis or the judgment of a licensed professional engineer.

Read the full use and limitation statement