Subtract recovery during the peak and clip negative preliminary storage to zero.
Equation legend
Inputs and calculated quantities
Vᵐ
Peak mixed-water demand — gal or L
tᵖ
Peak interval — h
Tᵐ
Mixed delivery temperature — °F or °C
Tᶜ
Cold-water temperature — °F or °C
Tʰ
Stored hot-water temperature — °F or °C
Rʰ
Recovery at storage temperature — gal/h or L/h
Vˢ
Preliminary net storage — gal
xʰ
Hot-water fraction — %
Vʰ
Equivalent stored-hot demand — gal
Vʳ
Recovered hot volume — gal
Applications
How this calculation is used
Building design
Screen preliminary net storage from a user-approved peak profile.
Construction
Check scheduled temperatures, recovery, and storage assumptions.
Commissioning
Document the design relationship before testing heater capacity and usable storage.
Quality controls
Assumptions and limitations
Assumptions
Entered values describe one documented system and use a consistent unit, energy, pressure, elevation, and measurement basis.
Measurements are representative and synchronized where the calculation combines field readings.
Limitations
Constant temperatures, ideal mixing, constant recovery, and one peak interval are assumed; draw profile, stratification, dead volume, standby/distribution loss, and redundancy are omitted.
Confirm the calculation boundary, source documents, formula symbols, and units.
Record representative field values or approved project inputs and their sources.
Review the result against the applicable code, criteria, manufacturer data, and measurement uncertainty.
Common engineering mistakes
Combining values from different system boundaries, operating periods, temperature bases, or unit conventions.
Treating a calculated screening value as a hidden pass/fail threshold or final design decision.
Technical basis
References and source standards
International Plumbing Code, 2024The legally adopted edition and local amendments govern water, sanitary, storm, sump, and pumping requirements; protected code tables are not reproduced.
ASSE Product Performance StandardsASSE 1017 and other applicable standards provide product context for hot-water mixing and temperature-control devices.
American Society of Plumbing EngineersPlumbing design and engineering-method context; verify the current licensed reference and project criteria during professional review.
These engineering tools are provided for educational, preliminary evaluation, field verification, and commissioning support. Results depend on the accuracy of user-entered information and the assumptions stated for each calculation. Every colored status and comparison is a screening indicator only; project criteria, contract requirements, applicable codes, manufacturer instructions, measurement uncertainty, and authorized engineering judgment govern. The tools do not replace project-specific engineering analysis or the judgment of a licensed professional engineer.