ElectricalIntermediateStandby Power and Batteries

Battery Capacity Screening Calculator

Calculate ideal minimum amp-hour capacity for a constant AC load and required runtime.

Why it matters: The ideal inverse energy balance is useful for early planning but is not a selected battery string.

User inputs

Enter field measurements

6 inputs
Select I-P or SI display units. Electrical units remain unchanged unless a real conversion is identified.
kWConstant AC load for the ideal screen.
hUser-entered required operating duration.
VNominal battery-string DC voltage.
%User-entered conversion efficiency.
%User-entered usable fraction of nominal capacity.

Calculated result

Engineering evaluation

Calculation complete—verify project criteria
Ideal required battery capacity (Cʳ)57.87 Ah
Required nominal energy (Eʳ)
13.889 kWh

Engineering interpretation

The ideal screen requires 13.88889 kWh nominal energy or 57.87037 Ah at 240 V DC.

Important limitations

  • Ideal screening only. Exact manufacturer discharge data are mandatory for final use; do not round down or treat this value as a selected battery string.

Engineering knowledge center

Understand the calculation—not just the answer

2026-08-07 · Free Library
Governing relationships
Eʳ = Pᴸ·t/[(η/100)(DOD/100)]
Cʳ = 1000Eʳ/Vᴰᶜ
Current substitution

Eʳ = 5×2/[0.9×0.8] = 13.88889 kWh; Cʳ = 1000×13.88889/240 = 57.87037 Ah.

Calculation sequence

Step-by-step method

  1. Calculate required load energy.
  2. Divide by user-entered efficiency and usable depth.
  3. Convert nominal energy to ideal amp-hour capacity.

Equation legend

Inputs and calculated quantities

Pᴸ
AC load — kW
t
Required runtime — h
Vᴰᶜ
Nominal DC voltage — V
η
UPS/inverter efficiency — %
DOD
Usable depth of discharge — %
Cʳ
Ideal required battery capacity — Ah
Eʳ
Required nominal energy — kWh

Engineering calculation disclaimer

These engineering tools are provided for educational, preliminary evaluation, field verification, and commissioning support. Results depend on the accuracy of user-entered information and the assumptions stated for each calculation. Every colored status and comparison is a screening indicator only; project criteria, contract requirements, applicable codes, manufacturer instructions, measurement uncertainty, and authorized engineering judgment govern. The tools do not replace project-specific engineering analysis or the judgment of a licensed professional engineer.

Read the full use and limitation statement