ElectricalBeginnerEnergy and Demand

Demand-Charge Estimation Calculator

Estimate simple demand charges from a user-entered billing demand, rate, and number of periods.

Why it matters: Demand charges can be material, but the serving tariff—not a generic formula—defines the bill.

User inputs

Enter field measurements

4 inputs
Select I-P or SI display units. Electrical units remain unchanged unless a real conversion is identified.
kWUser-entered billing demand from the applicable tariff or bill.
currency/kW-periodUser-entered demand rate.
countWhole number of periods using the same rate and demand assumption.

Calculated result

Engineering evaluation

Calculation complete—verify project criteria
Estimated total demand charge (Cᵀ)90,000 currency
Demand charge per period (Cᵖ)
7,500 currency/period

Engineering interpretation

The simple demand-only screen is 7500 currency units per period and 90000 for 12 periods.

Important limitations

  • The serving tariff controls. Ratchets, TOU windows, seasons, coincident peaks, minimum bills, taxes, and PF adjustments are omitted unless represented in the entered values.

Engineering knowledge center

Understand the calculation—not just the answer

2026-08-07 · Free Library
Governing relationships
Cᵖ = Pᵇ·Rᵈ
Cᵀ = n·Pᵇ·Rᵈ
Current substitution

Cᵖ = 500×15 = 7500; Cᵀ = 12×7500 = 90000.

Calculation sequence

Step-by-step method

  1. Multiply user-entered billing demand by the demand rate.
  2. Multiply by the whole number of billing periods.
  3. Review the serving tariff before use.

Equation legend

Inputs and calculated quantities

Pᵇ
Billing demand — kW
Rᵈ
Demand rate — currency/kW-period
n
Number of billing periods — count
Cᵀ
Estimated total demand charge — currency
Cᵖ
Demand charge per period — currency/period

Engineering calculation disclaimer

These engineering tools are provided for educational, preliminary evaluation, field verification, and commissioning support. Results depend on the accuracy of user-entered information and the assumptions stated for each calculation. Every colored status and comparison is a screening indicator only; project criteria, contract requirements, applicable codes, manufacturer instructions, measurement uncertainty, and authorized engineering judgment govern. The tools do not replace project-specific engineering analysis or the judgment of a licensed professional engineer.