CommissioningBeginnerCross-Discipline Energy

Energy Cost Calculator

Estimate energy use and consumption cost from power, operating hours, load factor, and an entered energy rate.

Why it matters: Energy-cost screening should keep entered tariff assumptions separate from measured equipment performance.

User inputs

Enter field measurements

4 inputs
kWRepresentative electrical demand.
hOperating hours in the evaluation period.
%Average fraction of entered power during operating hours.
$/kWhApplicable marginal or blended energy rate; demand charges are excluded.

Calculated result

Engineering evaluation

Screening estimate complete
Estimated energy-consumption cost (K)18,000 $
Average operating power (Pavg)
75 kW
Estimated energy use (E)
150,000 kWh

Engineering interpretation

Estimated consumption is 150000 kWh at an energy cost of $18000. This screen excludes demand charges, fixed fees, taxes, ratchets, time-of-use periods, and escalation unless embedded in the entered rate.

Important limitations

  • Use the applicable utility tariff or marginal rate for decision-making; a blended bill rate may not represent avoided cost.

Engineering knowledge center

Understand the calculation—not just the answer

2026-08-07 · Free Library
Governing relationships
Pavg = P(LF/100)
E = Pavg H
K = EC
Current substitution

Pavg = 100(75/100) = 75 kW; E = 75×2000 = 150000 kWh; K = 150000×0.12 = $18000.

Calculation sequence

Step-by-step method

  1. Multiply entered power by average load factor.
  2. Multiply average power by operating hours.
  3. Multiply energy use by the entered energy rate.

Equation legend

Inputs and calculated quantities

P
Connected or measured power — kW
H
Operating hours — h
LF
Average load factor — %
C
Energy rate — $/kWh
K
Estimated energy-consumption cost — $
Pavg
Average operating power — kW
E
Estimated energy use — kWh

Engineering calculation disclaimer

These engineering tools are provided for educational, preliminary evaluation, field verification, and commissioning support. Results depend on the accuracy of user-entered information and the assumptions stated for each calculation. Every colored status and comparison is a screening indicator only; project criteria, contract requirements, applicable codes, manufacturer instructions, measurement uncertainty, and authorized engineering judgment govern. The tools do not replace project-specific engineering analysis or the judgment of a licensed professional engineer.

Read the full use and limitation statement